Kim Son Technology Service

Structural Replacement of Boom Braces

Project Overview

Kim Son Technology Service Co., Ltd was appointed by Sarens to execute the critical structural replacement of two (02) boom braces on a heavy-duty WO-Luffer crane (Crane Model/Serial No. 11 020). Works were performed on-site under strict safety and quality protocols to ensure zero disruption to the ongoing project schedule.

Scope of Work

1. Preparation

    • New boom braces fabricated from certified high-strength steel with full material certificates
    • Welding electrodes dried at 350 °C for 2 hours in controlled oven

2. Removal & Surface Preparation

      • Safe removal of existing boom braces
      • Precision grinding of boom chord connection surfaces
      • Magnetic Particle Inspection (MPI) Level II performed on all prepared surfaces – no defects found

3. Fit-up & Welding

    • Accurate fit-up of two new boom braces with temporary strongbacks
    • Preheating of joint areas to required temperature
    • Multi-pass welding executed by DNV/GL & AWS-certified welders using approved WPS/PQR
    • Strict inter-pass temperature control maintained

4. Post-Weld Inspection (after minimum 24-hour hold)

      • 100 % MPI on all four (04) welded joints
      • Zero indications – all joints accepted as per code requirements

The Result

The boom structure was restored to full design strength and certified for continued heavy-lifting operations. All welding and NDT records, material certificates, and inspection reports were compiled into a comprehensive handover dossier for Sarens and the end client.

Date
25 November, 2023

Client
Sarens

Location
Quang Binh